Davis Contractors Ltd v Fareham Urban District Council [1956] is the seminal authority for the “radically different” test for frustration.
Facts of the Case
In July 1946, Davis Contractors agreed to build 78 houses for Fareham UDC within eight months for a fixed £94,425. A pre-contract letter said the tender was “subject to adequate supplies of labour being available”. A post-war shortage of skilled labour meant the project took 22 months and cost £115,233. Fareham paid the contract price; Davis sued for an additional £17,651, arguing the letter was a term Fareham had breached, or that the contract had been frustrated, entitling them to a quantum meruit.
Legal Issues
- Was the 18 March letter on labour availability incorporated into the contract?
- Did the labour shortage and delay frustrate the contract?
- Could a party rely on frustration because performance became more onerous or expensive?
The Judgment
The House of Lords unanimously dismissed the appeal. The letter was not incorporated (and even if it were, would only have excused delay, not justified a higher price). The plea of frustration was rejected: the delay, though significant, did not make the obligation “radically different” from what was undertaken.
Key Legal Principles
- The “radically different” test: Lord Radcliffe held frustration occurs only when, without fault, performance becomes a thing “radically different from that which was undertaken by the contract”.
- Rejection of the “implied term” theory: the court moved away from the Taylor v Caldwell fiction toward a “construction theory” focused on the true meaning of the contract.
- Hardship is not frustration: mere hardship, inconvenience or material loss does not frustrate; frustration is “not to be lightly invoked” to rescue a party from an “imprudent bargain”.
- Foreseeability and risk: the post-war labour shortage was a foreseeable risk the contractors had assumed by not including a protective clause.
Authority and Significance
Davis Contractors is the primary standard for frustration in modern English law, a strict warning that increased expense or difficulty is a normal commercial risk, and the foundation of the restrictive approach that prevents frustration becoming an escape route from a bad bargain.
Related Cases
- Taylor v Caldwell (1863): the origin of the modern doctrine, resting on the older “implied term” theory.
- British Movietonews Ltd v London and District Cinemas Ltd: courts have no general “absolving power” to vary contracts that become more onerous.
- The Nema (Pioneer Shipping Ltd v BTP Tioxide Ltd): frustration is “not lightly to be invoked to relieve contracting parties of the normal consequences of imprudent bargains”.
- The Sea Angel (Edwinton Commercial Corp v Tsavliris Russ Ltd): refined the test as “multi-factorial”, weighing contract terms, knowledge of risk and the nature of the event.